April 8, 2022

National Grid’s contractor, Creamer Environmental, has completed remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design.    National Grid will continue to conduct recovery of NAPL from wells and groundwater monitoring.  The cleanup activities were performed with oversight by the New York State Department of Environmental Conservation (NYSDEC).

Overview:

On-going activities:

Recently completed activities:

Upcoming work activities:

Community Air Monitoring Plan Summary

For the period 03/24/22 through 04/01/22 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.  Community air monitoring was discontinued on 04/01/22, as approved by the NYSDEC and NYSDOH following the completion of earth disturbing activities. 


Final grading and restoration of the Parcel I supplemental excavation.


Demobilizing equipment and supplies.