National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed in early 2022. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of recovery wells on Parcel II.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Installation of recovery wells on Parcel III.
Upcoming work activities:
- Removal of the Parcel I supplemental excavation support of excavation system sheet piles.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 12/23/21 through 12/29/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Backfilling the Parcel I supplemental excavation.
Installation of recovery wells on Parcel II.
December 24, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed in early 2022. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of recovery wells on Parcel III.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Placing backfill behind the bulkhead barrier wall closure.
- Installation of the bulkhead barrier wall closure upper and lower wales.
Upcoming work activities:
- Backfilling within the Parcel I supplemental excavation support of excavation system to subgrade elevation.
- Installation of recovery wells on Parcel II.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 12/16/21 through 12/22/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of recovery wells on Parcel III.
Installation of the bulkhead barrier wall closure.
December 17, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed in early 2022. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of the bulkhead barrier wall closure upper and lower wales.
- Installation of recovery wells on Parcel III.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
Upcoming work activities:
- Placing backfill behind the bulkhead barrier wall closure.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 12/09/21 through 12/15/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of recovery wells on Parcel III.
Installation of the bulkhead barrier wall closure.
December 3, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed in early 2022. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of recovery wells on Parcel III.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Installation of the bulkhead barrier wall closure upper wale at the gas shaft.
Upcoming work activities:
- Installation of the bulkhead barrier wall closure lower wale at the gas shaft.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 11/25/21 through 12/01/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of recovery wells on Parcel III.
Installation of the bulkhead barrier wall closure upper wale at the gas shaft.
November 26, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of product recovery wells and piezometers on Parcel III.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Installation of the bulkhead barrier wall closure piles at the gas shaft.
Upcoming work activities:
- Installation of the bulkhead barrier wall closure wales at the gas shaft.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 11/18/21 through 11/24/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of piezometers and recovery wells on Parcel III.
Installation of bulkhead barrier wall closure piles at the gas shaft.
November 19, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of product recovery wells and piezometers on Parcel III.
- Installation of the driving template for the bulkhead barrier wall closure at the gas shaft.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Receipt of bulkhead barrier wall closure materials.
- Probing to identify obstructions along the bulkhead closure alignment.
Upcoming work activities:
- Installation of the bulkhead barrier wall closure piles at the gas shaft.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 11/11/21 through 11/17/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of piezometers and recovery wells on Parcel III.
Mobilization of bulkhead barrier wall closure materials.
November 12, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, and the installation of a noise mitigation barriers.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of the bulkhead barrier wall cap on Parcel II.
- Transportation of materials off-site for disposal and recycling.
- Probing to identify obstructions along the bulkhead closure alignment.
Recently completed activities:
- Removal of the support of excavation bracing system in the Parcel I supplemental excavation area.
Upcoming work activities:
- Installation of product recovery wells and piezometers.
- Installation of the bulkhead barrier wall closure piles at the gas shaft.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 10/28/21 through 11/03/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Probing to identify obstructions along the bulkhead closure alignment at the gas shaft.
Installation of the bulkhead barrier wall cap on Parcel II.
November 5, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures from the Parcel I supplemental excavation area.
- Removal of the support of excavation bracing system in the Parcel I supplemental excavation area.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of the bulkhead barrier wall cap on Parcels II.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Installation of the bulkhead barrier wall cap on Parcel III.
Upcoming work activities:
- Installation of product recovery wells and piezometers.
- Installation of the bulkhead barrier wall closure at the gas shaft.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 10/28/21 through 11/03/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) associated with Site activities. On 11/01/21 there were two 15-minute periods when Particulate Matter (PM-10) concentrations were above the Action Limit. The elevated PM-10 concentrations were caused by the exhaust from an operating truck blowing directly into an air monitoring station. The truck was moved and no additional levels greater than the 15-minute Action Level for PM-10 occurred during the reporting period.
Removal of the support of excavation bracing from the Parcel I supplemental excavation.
Installation of the bulkhead barrier wall cap on Parcel II.
October 29, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures within the Parcel I supplemental excavation to final elevation.
- Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
- Installation of the bulkhead barrier wall cap on Parcels II and III.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
Upcoming work activities:
- Removal of the support of excavation bracing system in the Parcel I supplemental excavation area.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 10/21/21 through 10/27/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Excavation of material from the Parcel I supplemental excavation and backfilling completed portion with general fill.
Installation of the bulkhead barrier wall cap on Parcel III.
October 22, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures within the Parcel I supplemental excavation to final elevation.
- Installation of the bulkhead barrier wall cap.
- Transportation of materials off-site for disposal and recycling.
- Final grading and placement of crushed stone surface along Parcel II bulkhead barrier wall.
Recently completed activities:
- Installation of the support of excavation system bracing within the Parcel I supplemental excavation.
Upcoming work activities:
• Backfilling the Parcel I supplemental excavation as sections are completed to the design depth.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 10/14/21 through 10/20/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Excavation and loadout of material from the Parcel I supplemental excavation.
Installation of the bulkhead barrier wall cap.
October 15, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Installation of bulkhead barrier wall cap.
- Installation of the support of excavation system bracing within the Parcel I supplemental excavation.
- Transportation of materials off-site for disposal and recycling.
- Final grading and placement of crushed stone surface along Parcel II and III bulkhead barrier wall.
Recently completed activities:
Upcoming work activities:
- Excavation of soil and demolition of subsurface structures within the Parcel I supplemental excavation to final elevation (following installation of bracing system).
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 10/06/21 through 10/13/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of the support of excavation bracing system within the Parcel I supplemental excavation.
Installation of the bulkhead barrier wall cap on Parcel III.
October 1, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of soil and demolition of subsurface structures within the Parcel I supplemental excavation.
- Transportation of materials off-site for disposal and recycling.
- Final grading and placement of crushed stone surface along Parcel II and III bulkhead barrier wall.
Recently completed activities:
- Demolition of surficial concrete within the Parcel I supplemental excavation footprint.
Upcoming work activities:
- Installation of bulkhead barrier wall cap.
- Installation of the support of excavation system bracing within the Parcel I supplemental excavation.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 09/23/21 through 09/29/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
Final grading and placement of crushed stone surface along Parcel III bulkhead barrier wall.
September 17, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Installation of sheet piles around the perimeter of the Parcel I supplemental excavation.
- Final grading and placement of crushed stone surface along Parcel II bulkhead barrier wall.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Mobilization of sheet pile installation equipment.
- Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
Upcoming work activities:
- Excavation of soil and demolition of structures within Parcel I supplemental excavation.
- Installation of bulkhead barrier wall cap.
- Final grading and placement of crushed stone surface on Parcel III.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 09/09/21 through 09/15/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
Installation of sheet piles around the perimeter of the Parcel I supplemental excavation.
September 10, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Demolition of surficial concrete around perimeter of Parcel I supplemental excavation area in preparation for pre-trenching and sheet pile installation.
Upcoming work activities:
- Mobilization of sheet pile installation equipment.
- Installation of sheet piles around the perimeter of the Parcel I supplemental excavation.
Surficial concrete demolition around perimeter of Parcel I supplemental excavation in advance of pre-trenching and sheet pile installation.
Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
Sound barrier.
September 3, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Demolition of surficial concrete from Parcel I supplemental excavation area.
- Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Construction of equipment pad in preparation for installation of sheet pile installation.
Upcoming work activities:
- Mobilization of sheet pile installation equipment.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. For the period 08/26/21 through 09/01/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Surficial concrete demolition and construction of equipment pad for Parcel I supplemental excavation.
Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
August 27, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Demolition of surficial concrete from Parcel 1 supplemental excavation area.
- Transportation of materials off-site for disposal and recycling.
Recently completed activities:
- Remobilization of equipment, personnel, and supplies to the Site.
- Installation of geotechnical instrumentation.
- Installation of temporary sound barrier on Parcel I.
- Loadout of stockpiled material from Parcel III for disposal.
- Relocation of equipment decontamination pad.
Upcoming work activities:
- Pre-trenching the sheet pile alignment for the Parcel I supplemental excavation.
Community Air Monitoring Plan Summary
Continuous community air monitoring is on-going. Community air monitoring activities resumed on August 11, 2021. For the period 08/19/21 through 08/25/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Demolition and loadout of surficial concrete from Parcel 1 supplemental excavation area.
Installation of temporary sound barrier on Parcel I.
August 20, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Remobilization of equipment, personnel, and supplies to the Site.
- Transportation of materials off-site for disposal and recycling.
- Installation of geotechnical instrumentation.
Recently completed activities:
- Installation of community air monitoring system.
Upcoming work activities:
- Parcel 1 supplemental excavation surficial concrete removal
Community Air Monitoring Plan Summary
Community air monitoring activities resumed on August 11, 2021. For the period 08/11/2121 through 08/18/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities.
Installation of community air monitoring station on Parcel III.
Loadout of stockpiled soil for offsite disposal.
August 13, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the end of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Remobilization of equipment, personnel, and supplies to the Site.
- Installation of community air monitoring system.
Recently completed activities:
Upcoming work activities:
- Transportation of materials off-site for disposal and recycling
- Parcel 1 supplemental excavation surficial concrete removal
Community Air Monitoring Plan Summary
Community air monitoring activities resumed on August 11, 2021.
May 28, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Operations on-site currently paused pending permit approvals
Recently completed activities:
- Temporary demobilization from site
Upcoming work activities:
- Transportation of materials off-site for disposal and recycling
- Parcel 1 supplemental excavation
Community Air Monitoring Plan Summary
Community air monitoring on-site currently paused pending resumption of operations.
May 21, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Operations on-site currently paused pending permit approvals
Recently completed activities:
- Pump pit excavation on Parcel 3
- Temporary demobilization from site
Upcoming work activities:
- Transportation of materials off-site for disposal and recycling
- Parcel 1 supplemental excavation
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 05/13/21 through 05/21/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Backfilling pump pit excavation on Parcel 3.
Demobilization of 3 office trailers.
May 14, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Pump pit excavation on Parcel 3
- General site clean-up on Parcel 1
- Demobilization of certain on-site facilities
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Installation of crushed stone surface on Parcel 1
- Bulkhead coating touch-up on Parcel 2 and 3
Upcoming work activities:
- Parcel 1 supplemental excavation
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 05/06/21 through 05/12/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Pump pit excavation on Parcel 3.
Pump pit excavation on Parcel 3.
May 7, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Pump pit excavation on Parcel 3
- General site clean-up on Parcel 1
- Demobilization of certain on-site facilities
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Installation of crushed stone surface on Parcel 1
- Bulkhead coating touch-up on Parcel 2 and 3
Upcoming work activities:
- Parcel 1 supplemental excavation
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 04/29/21 through 05/05/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 04/22/21 through 04/28/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Completed bulkhead coating touch-up on Parcel 3.
Pump pit excavation on Parcel 3.
April 30, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Demobilization of water treatment system
- Demobilization of support of excavation materials
- Demobilization of certain on-site facilities
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Grading Parcel 1 soil remediation areas
- Installation of crushed stone surface on Parcel 1
Upcoming work activities:
- Pump pit excavation on Parcel 3
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 04/22/21 through 04/28/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Installation of crushed stone on Parcel 1.
Demobilization of water treatment system components.
April 23, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Grading Parcel 1 soil remediation areas
- Installation of crushed stone surface on Parcel 1
- Demobilization of water treatment system
- Demobilization of support of excavation materials
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Removal of temporary support of excavation steel sheeting on Parcel 1
Upcoming work activities:
- Temporary demobilization from the Site
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 04/15/21 through 04/21/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Installation of crushed stone subbase on Parcel 1.
Load out of Parcel 1 soil for off-site disposal.
April 9, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Grading Parcel 1 soil remediation areas
- Removal of temporary support of excavation steel sheeting on Parcel 1
- Demobilization of water treatment system
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Removal of temporary membrane structure on Parcel 1
- Backfilling of fourth phase of Parcel 1 soil remediation area
Upcoming work activities:
- Installation of crushed stone surface on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 04/01/21 through 04/07/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Removal of temporary support of excavation sheet piling on Parcel 1.
Backfilling of fourth phase of Parcel 1 soil remediation area.
April 2, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Backfilling of fourth phase of Parcel 1 soil remediation area
- Removal of support of excavation steel sheeting on Parcel 1
- Demobilization of water treatment system
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Removal of temporary membrane structure on Parcel 1
Upcoming work activities:
- Installation of crushed stone surface on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 03/25/21 through 03/31/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) associated with Site activities. On March 26, 2021, elevated PM-10 concentrations were detected by the perimeter air monitoring stations on the site. The PM-10 concentrations were above the Alarm Level at all three perimeter air monitoring stations. There was a smell of and visible smoke on the Site coming from the south-southeast. The offsite source of the smoke was not identified. The elevated PM-10 concentrations lasted for more than 45 minutes.
Removal of temporary support of excavation sheet piling on Parcel 1.
Excavation to expose temporary support of excavation sheet piling on Parcel 1.
March 26, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Backfilling of fourth phase of Parcel 1 soil remediation area
- Removal of support of excavation steel sheeting on Parcel 1
- Demobilization of water treatment system
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Removal of temporary membrane structure on Parcel 1
Upcoming work activities:
- Installation of crushed stone surface on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 03/18/21 through 03/24/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Removal of temporary membrane structure master bay on Parcel 1.
Demobilization of water treatment system.
March 12, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Backfilling of fourth phase of Parcel 1 soil remediation area
- Removal of temporary membrane structure on Parcel 1
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Removal of support of excavation bracing from fourth phase of Parcel 1 soil remediation area
Upcoming work activities:
- Removal of support of excavation steel sheeting on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 03/04/21 through 03/10/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Removal of support of excavation bracing from fourth phase of Parcel 1 soil remediation area.
Removal of temporary membrane structure on Parcel 1.
March 5, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Backfilling of fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Removal of vapor management system for the temporary membrane structure on Parcel 1
Upcoming work activities:
- Removal of temporary membrane structure on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 02/24/21 through 03/03/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Backfilling fourth phase of Parcel 1 soil remediation area.
Demobilization of vapor management system for temporary membrane structure on Parcel 1.
February 26, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation and backfilling of fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
Upcoming work activities:
- Removal of temporary membrane structure on Parcel 1
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 02/18/21 through 02/23/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Excavation of fourth phase of Parcel 1 soil remediation area.
Excavation of fourth phase of Parcel 1 soil remediation area.
February 19, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
Upcoming work activities:
- Restoration adjacent to bulkheads
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 02/11/21 through 02/17/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10).
Excavation of fourth phase of Parcel 1 soil remediation area.
Excavation of fourth phase of Parcel 1 soil remediation area.
February 12, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
Upcoming work activities:
- Restoration adjacent to bulkheads
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 02/04/21 through 02/10/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC). On 02/05/20, there was one 15-minute level above the Action Limit for Particulate Matter (PM-10) after work hours [unknown off-site source] within the western Site boundary along Smith Street. No additional levels above the 15-minute Action Limit for PM-10 occurred during the reporting period.
Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area.
February 5, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Relocation of temporary membrane structure to fourth phase of Parcel 1 soil remediation area
- Backfilling of third phase of Parcel 1 soil remediation area
Upcoming work activities:
- Restoration adjacent to bulkheads
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 01/28/21 through 02/03/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].
Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area.
Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area.
January 29, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Relocation of temporary membrane structure to fourth phase of Parcel 1 soil remediation area
- Backfilling of third phase of Parcel 1 soil remediation area
Upcoming work activities:
- Restoration adjacent to bulkheads
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 01/21/21 through 01/27/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].
Excavation of fourth phase of Parcel 1 soil remediation area.
Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area.
January 22, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Relocation of temporary membrane structure to fourth phase of Parcel 1 soil remediation area
- Backfilling of third phase of Parcel 1 soil remediation area
Upcoming work activities:
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 01/14/21 through 01/20/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].
Installation of temporary membrane structure vapor management system ducting.
Excavation of fourth phase of Parcel 1 soil remediation area.
January 15, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Relocation of temporary membrane structure to fourth phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Backfilling of third phase of Parcel 1 soil remediation area
Upcoming work activities:
- Excavation of fourth phase of Parcel 1 soil remediation area
- Installation of support of excavation bracing for fourth phase of Parcel 1 soil remediation area
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 01/07/21 through 01/13/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].
Backfilling of third phase of Parcel 1 soil remediation area.
Relocation of temporary membrane structure to fourth phase of Parcel 1 soil remediation area.
January 8, 2021
National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design. Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021. The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC). Community air monitoring and vibration monitoring are being conducted during this project.
Overview:
- The key elements of the remediation work include excavation of MGP Site impacted soils and installation of bulkheads using heavy construction equipment.
- Preparation for these key remediation elements requires sheet pile installation to support excavations on site, as well as construction of bulkheads along the Gowanus Canal.
- There are established measures to reduce potential noise, vibration, and dust from the work including pre-drilling before sheet pile driving, installation of a noise mitigation wall, and the use of temporary enclosed fabric structures with air handling systems to control air emissions from the excavation work within the fabric structure.
- Air, noise, and vibration monitoring are conducted each day to ensure that the work is conducted in accordance with the requirements of NYSDEC, NYSDOH and NYC.
On-going activities:
- Backfilling of third phase of Parcel 1 soil remediation area
- Transportation of materials off-site for disposal and recycling
Recently completed activities:
- Removal of support of excavation bracing from third phase of Parcel 1 soil remediation area
Upcoming work activities:
- Relocation of temporary membrane structure to forth phase of Parcel 1 soil remediation area
Community Air Monitoring Plan Summary
Continued community air monitoring. For the period 12/28/20 through 01/06/21 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].
Removal of support of excavation from third phase of Parcel 1 soil remediation area.
Backfilling of third phase of Parcel 1 soil remediation area.