June 19, 2020

National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design.  Mobilization began on July 10, 2019 and the remedial activities are expected to be completed by the middle of 2021.  The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC).  Community air monitoring and vibration monitoring are being conducted during this project.

Overview:

On-going activities:

Recently completed activities:

Upcoming work activities:

Community Air Monitoring Plan Summary

Continuous community air monitoring is on-going.  For the period 06/10/20 through 06/17/20 there were no levels above the 15-minute Action Limit for Total Volatile Organic Compounds (TVOC) or Particulate Matter (PM-10) [dust].   


Installation of Parcel 1 controlled low strength material gravity wall.


Removal of Parcel 3 temporary membrane structure.