August 30, 2019

National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site to address MGP Site related impacts in accordance with the NY State DEC approved design.  Mobilization began on July 10, 2019 and the remedial activities are expected to take about 2 years to complete.  The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC).  Community air monitoring and vibration monitoring will be conducted during this project.

On-going activities:

Recently completed activities:

Upcoming work activities:

Community Air Monitoring Plan Summary

Continuous community air monitoring is on-going.  For the period 8/22/19 through 8/28/19 there was no 15-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC).  On 8/27, there was a 15-minute Action Limit exceedance for Particulate Matter (PM-10) [dust] within the Site boundary at the east end of Huntington Street.  Additional dust mitigation consisting of increased water application in the work area was implemented immediately following notification of the elevated PM-10 concentrations.  No additional 15-minute Action Limit exceedances for PM-10 occurred during the reporting period.   


Geotechnical instrumentation installation


Re-grading of soil remediation area