July 26, 2019

National Grid’s contractor, Creamer Environmental, is implementing remedial actions at the Citizens former Manufactured Gas Plant (MGP) Site that will address the MGP Site related impacts in accordance with the NY State DEC approved design.  Mobilization began on July 10th and the remediation will require about 2 years to complete.  The cleanup activities are being performed with oversight by the New York State Department of Environmental Conservation (NYSDEC).  Community air monitoring and vibration monitoring will be conducted during this project.

On-going activities:

Upcoming work activities:

Community Air Monitoring Plan Summary

Baseline monitoring conducted from July 15 through 24, 2019.  There were no 15-minute Action Limit exceedances for Total Volatile Organic Compounds (TVOC) and Particulate Matter (PM-10) [dust] during the baseline monitoring program.